|
Mahira Homes 103 : - Construction Work Status (17th May 2023) |
| Sr.No. |
Towers |
Construction Status |
| 1 |
Tower A |
PCC Completed, De-Watering Work in Progress. |
| 2 |
Tower B |
8th Floor Level Completed. |
| 3 |
Tower C |
10th Floor Level Completed & 11th Floor Level Part-1 is Ready for Casting & 2nd Part Steel Work in Progress. |
| 4 |
Tower D |
12th Floor Level Completed & 13th Floor Level Wall & Column Steel Complete & Shuttering Work in Progress. |
| 5 |
Tower E |
10th Floor Completed & 11th Floor Level Wall & Column Steel Complete & Shuttering Work in Progress. |
| 6 |
Tower F |
1st Floor Level Completed. |
| 7 |
Tower G |
1st Floor Level Completed. |
| 8 |
Tower H |
1st Floor Level Part-1 Completed. |