Sr. No.
|
Towers
|
Construction Status
|
1
|
Tower-A
|
Tile Work
- 95%
Internal Paint
- 60%,
External
Paint 1st Coat -100%
Door Frame
Fixing - 100%
Door
Shutter Fixing - 90%
Glass
Fixing - 100%
|
2
|
Tower-B
|
Tile Work - 95%
Internal Paint - 60%,
External Paint 1st Coat -100%
Door Frame Fixing - 100%
Door Shutter Fixing - 90%
Glass Fixing - 100%
|
3
|
Tower-C
|
Tile Work - 95%
Internal Paint - 60%,
External Paint 1st Coat -95%
Plumbing Work - 100%
Door Frame Fixing - 100%
Door Shutter Fixing - 90%
Glass Fixing - 100%
|
4
|
Tower-D
|
Tile Work - 95%
Internal Paint - 60%,
Door Frame Fixing - 100%
External Paint 1st Coat - 100%
Plumbing Work - 100%
Glass Fixing - 100%
|
5
|
Tower-E
|
Tile Work - 70%
Internal Paint - 60%,
Door Frame Fixing - 80%
External Paint 1st Coat - 100%
Plumbing Work - 100%
|
6
|
Tower-F
|
Tile Work - 60%
Internal Paint - 50%,
Door Frame Fixing - 100%
External Paint 1st Coat - 60%
Plumbing Work - 100%
|
7
|
Tower-G
|
Parapet & machine room work in progress
(Structure) - 70%
Internal (1st coat putty) external Paint(primer) in progress - 80%
|
|
|
|
8
|
Tower-H
|
Ground to 1st floor work in progress
(Structural)
|
9
|
Tower-J
|
Up to plinth beam level work only
completed (Structural)
|
10
|
Tower-L
|
5th floor level slab in progress
(Structural)
|
11
|
Tower-M
|
12th floor level slab in progress
(Structural)
|
12
|
Tower-N
|
6th floor level slab in progress
(Structural)
|
13
|
External
Development
|
Sewer Line 50% completed, Boundary
wall work stable
|
14
|
STP
|
40% Raft Casting, 25 mtr Wall Casting
|