Mahira Homes 68: - Construction Work Status (9th May 2023)

 



Sr. No.



Towers



Construction Status





1





Tower-A

 

Tile Work - 95%

Internal Paint - 60%,

External Paint 1st Coat -100%

Door Frame Fixing - 100%

Door Shutter Fixing - 90%

Glass Fixing - 100%






2





Tower-B

 

Tile Work - 95%

Internal Paint - 60%,

External Paint 1st Coat -100%

Door Frame Fixing - 100%

Door Shutter Fixing - 90%

Glass Fixing - 100%

 





3





Tower-C

 

Tile Work - 95%

Internal Paint - 60%,

External Paint 1st Coat -95%

Plumbing Work - 100%

Door Frame Fixing - 100%

Door Shutter Fixing - 90%

Glass Fixing - 100%

 





4





Tower-D

 

Tile Work - 95%

Internal Paint - 60%,

Door Frame Fixing - 100%

External Paint 1st Coat - 100%

Plumbing Work - 100%

Glass Fixing - 100%

 




5




Tower-E

 

Tile Work - 70%

Internal Paint - 60%,

Door Frame Fixing - 80%

External Paint 1st Coat - 100%

Plumbing Work - 100%





6




Tower-F

 

Tile Work - 60%

Internal Paint - 50%,

Door Frame Fixing - 100%

External Paint 1st Coat - 60%

Plumbing Work - 100%




7



Tower-G

 

Parapet & machine room work in progress (Structure) - 70%

Internal (1st coat putty)  external Paint(primer) in progress - 80%

 

 

 


8


Tower-H

 

Ground to 1st floor work in progress (Structural)



9


Tower-J

 

Up to plinth beam level work only completed (Structural)



10


Tower-L

 

5th floor level slab in progress (Structural)



11


Tower-M

 

12th floor level slab in progress (Structural)



12


Tower-N

 

6th floor level slab in progress (Structural)



13


External Development

 

Sewer Line 50% completed, Boundary wall work stable



14


STP


40% Raft Casting, 25 mtr Wall Casting